Skip to Content or Accessibility Information

City Construction Projects

Are you curious about what construction projects are taking place throughout Prescott? Well, you've come to the right place! Below you will find a list of construction projects that are currently underway as well as those projects that are still pending.

For information on the status of construction projects please call the City of Prescott Public Works Department at 928-777-1130.

Projects in Design Phase

The project replacement of approximately 15,600 Lineal Feet (LF) of 24-inch to 48-inch gravity sewer trunk and branch mains near the Airport in the north Prescott area. The trunk main design will begin at the Airport Water Reclamation Facility and will run southerly to the Northern edge of the Granite Dells. (See Vicinity Map below).

This project will research alternative alignments while replacing the trunk main through the Airpark Industrial Park, under the State Route 89A /Larry Caldwell Interchange, including connections to the existing trunk main in State Route 89 at the north end of Granite Dells.

Results of the Sewer Model Report and Centralization Analysis, determined that the existing Airport Trunk Main needs to be upsized for current flow demands and for the centralized build out scenario. This project is the 5th of 10 projects that will complete centralization of the Wastewater Treatment process.

Centralization, when completed will combine all wastewater treatment processes at the Airport Water Reclamation Facility and decommission the Sundog Wastewater Treatment Plant.
The Airport Trunk Main, Phase 1 project was completed through the Walden Ranch Subdivision based on a cooperative agreement with Walden Ranch, in July 2017.

Last updated: Thursday, November 16, 2017 at 10:16 AM

PDF Project Update      Traffic Update / Street Closure not available

This project is scheduled for design build in the spring of 2018.

Statements of qualification have been received and will be reviewed according to Arizona State Statutes. A Design Build Team should be selected for Contract in the winter of 2018.

Last updated: Monday, November 27, 2017 at 4:04 PM

PDF Project Update      Traffic Update / Street Closure not available

The Bashford Courts Alley Reconstruction Project generally consists of reconstructing the severely deteriorated concrete and asphalt pavement in the alley bounded by Montezuma Street, Cortez Street, and Willis Street and the parking lot. As part of the project, an underground stormwater drainage system and sewer replacement is being included in the design of the project.

PDF Community Open House Invitation March 29, 2017

Last updated: Tuesday, November 28, 2017 at 10:28 AM

PDF Project Update      Traffic Update / Street Closure not available

The Carleton Street/Alarcon Street Improvements Project generally consists of reconstructing the severely deteriorated concrete roadway on Carleton Street from Montezuma Street to Cortez Street with new asphalt pavement. Water and sewer replacements, pavement improvements, landscaping and drainage improvements are also included throughout the project limits. Curb and sidewalk improvements will be included as needed. The limits are on Carleton Street from the entrance of Mile High Middle School to Alarcon Street, and Alarcon Street from Carleton Street to Aubrey Street.

City Contact Information Project Manager: Jeff Low 777-1643

Last updated: Tuesday, November 28, 2017 at 1:18 PM

PDF Project Update      Traffic Update / Street Closure not available

This project is currently under a Design Build Contract with Fann Contracting and Dibble Engineering. Guaranteed Maximum Price has been negotiated and the project should go to Council December 19, 2017. Construction for Chino Well #5 should begin in January, 2018 and conclude in May, 2018.

Project Manager Benjamin Burns (928) 777-1130

Last updated: Monday, November 27, 2017 at 4:10 PM

PDF Project Update      Traffic Update / Street Closure not available

Dameron Drive pavement will be reconstructed from Hillside Avenue to Comfort Avenue. Curb and sidewalk will not be removed in the northern portion. Role curb will be added on Dameron Drive from Brannen Avenue to Comfort Avenue.

Home Street will receive new pavement with drainage improvements and rolled curb. Lincoln Avenue from Home Street to Comfort Avenue will receive a new rolled curb on the west side which should help direct storm water flow to Comfort Avenue.

Last updated: Monday, November 27, 2017 at 4:13 PM

PDF Project Update      Traffic Update / Street Closure not available

The FY 2018 Pavement Preservation Project generally consists of Type II Slurry Seal, Type III Microsurfacing and a cape seal consisting of rubberized chip seal topped off with Type III Microsurfacing as well as Asphalt Maltene Rejuvenating Agent and Fog Seal, crack sealing on an as needed basis, pavement repairs and the restoration of disturbed traffic striping on streets throughout the city. The project also includes curb, gutter, handicap ramps, and valley gutter replacements.

City Contact Information Project Manager: Steve Guizzo Phone 777-1670

Last updated: Tuesday, November 28, 2017 at 11:06 AM

PDF Project Update      Traffic Update / Street Closure not available

The FY 2018 Pavement Rehabilitation Project generally consists of milling existing asphalt pavement and replacing with new asphalt pavement on Willow Creek, Sunrise Boulevard and West Hillside Ave. The work includes crack sealing on an as needed basis, pavement repairs, the adjustment of utility covers to finish grade, and the restoration of disturbed traffic striping. The project also includes curb, gutter, handicap ramps, and valley gutter replacements at various locations.

City Contact Information Project Manager: Steve Guizzo Phone 777-1130

Last updated: Tuesday, November 28, 2017 at 11:06 AM

PDF Project Update      Traffic Update / Street Closure not available

This project generally includes the replacement of approximately 2,700 square feet of concrete sidewalks, and the upgrade of 8 handicap ramps in the Prescott downtown area. The work also includes milling, grinding, or precision saw cutting to remediate uplifted sidewalk panels and miscellaneous curb and gutter replacements and repairs.

Last updated: Tuesday, November 28, 2017 at 11:25 AM

PDF Project Update      Traffic Update / Street Closure not available

This project generally includes the replacement of approximately 12,000 square feet of concrete sidewalks, and installation of safety handrail in the Prescott downtown area. The work also includes milling, grinding, or precision saw cutting to remediate uplifted sidewalk panels.

Last updated: Tuesday, November 28, 2017 at 11:24 AM

PDF Project Update      Traffic Update / Street Closure not available

This design contract is scheduled to go to Council in January, 2018.

This project will design new water main infrastructure to replace the undersized and aged water mains located in two areas of Prescott. Area one is located in the Mile High Park Addition which includes Mile High Drive, Rose Garden Cove, Keen Street and Paar Drive. Approximately 2,790 LF of various size water mains will be replaced in this location.

Area two is located along Karen Drive, Terrace Drive, Juniper Drive and Old Senator Highway. Approximately 5,000 LF of various size water mains will be installed in this area.

Last updated: Monday, November 27, 2017 at 4:18 PM

PDF Project Update      Traffic Update / Street Closure not available

The project is currently under design and has been awarded to Kimley-Horn.

The project consists of various drainage improvements associated with street drainage and neighborhood complaints regarding drainage. The following projects are under design: -Alarcon Alley #1 between Aubrey St. south to Lereaux St. - Project is to address drainage and sediment concerns associated with the alley.

-Robinson Drive Storm Drain off Hill Crest Lane. Drainage in the alley currently ponds for months and one house is known to flood in the area. A new storm drain is being design to convey drainage into the Robinson Drive storm drain system. The alleys in the area will be paved with the project. -915 Country Club Drive - Re-design the driveway (which has been elevated over the years with pavement overlays) and drainage along the side of the road. -Divinity Circle - Remove and repave the cul-de-sac. The road is failing and drainage is currently ponding in the road during storm events. -1816 Boardwalk Avenue - reinstall scupper drain to low point of the road. Currently, the scupper drain is not in the low point of the road and drainage jumps the curbing causing erosion damage near a culvert the City maintains. -5587 Goldenrod Way - Repair erosion hazard and re-install an outlet structure that has been undermined.
-Samaritan Way between Lakeview Road and Magnolia Lane -Grated drains are failing along the side of the road and the road in the area is deteriorating. The project will reinstall new grated drains and remove poor pavement sections before repaving the road. -Thumb Butte Road between 1803 and 1717 -Add curbing along the south side of the road, to prevent drainage from flooding houses and yards.

The project is currently at 90% design and is anticipated to start construction in the Spring. Based on the overall cost estimate not all of the projects being design above will be constructed within the 2018 budget.

Last updated: Tuesday, November 28, 2017 at 10:52 AM

PDF Project Update      Traffic Update / Street Closure not available

The Goodwin Street Improvements Project generally consists of constructing roadway, streetscaping and pedestrian access improvements along E. Goodwin Street from Summit Street east to Marina Street, and along Summit between Goodwin and Hill Streets. Water, sewer and the addition of storm drains are also included.

Hoskin-Ryan Consultants is the design engineer for this project.

Three public meetings are anticipated with the design. The first meeting was completed in March of last year to gather input from property owners, prior to the beginning of the project. Currently, Hoskin-Ryan Consultants has completed the 30% design plans. The second public meeting will be schedule after City staff's review of the 60% design plans.

City Contact Information Project Manager: Jeff Low Phone 777-1643

PDF Goodwin Street Open House March 1, 2017

Last updated: Tuesday, November 28, 2017 at 10:53 AM

PDF Project Update      Traffic Update / Street Closure not available

The Granite Creek Dam Outlet Rehabilitation Project generally consists of the replacement of the inoperable 36" large diameter valve that controls discharges for Watson Lake, and the sealing and abandonment of the inoperable 48" large diameter valve, both at Granite Creek Dam constructed in 1919. The proposed 36" replacement valve is to include a 12" bypass. The project will provide for operation of the valves from the dam crest via flexible operators. The project also includes the replacement of existing upstream trash racks and installation of new slide gates.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Tuesday, November 28, 2017 at 1:38 PM

PDF Project Update      Traffic Update / Street Closure not available

The Hassayampa Village Lane Intersection Improvements Project generally consists of improvements to drivability and site distance on Hassayampa Village Lane at the intersection with Thumb Butte Road. The goal of the project is to reduce the grade differential to allow for safer travel through the intersection.

City Contact Project Manager: George Henderson (928) 777-1130

Last updated: Tuesday, November 28, 2017 at 1:38 PM

PDF Project Update      Traffic Update / Street Closure not available

The Hope Street Improvements Project generally consists of constructing roadway, water main replacement and drainage improvements along Hope Street from White Spar Road to Warne Street. Additionally, the water main will be removed and replaced in Warne Street to loop into Hope Street.

Woodson Engineering was selected as the design engineer for this project. The engineering design contract was awarded at the July 14, 2015 City Council meeting.

Woodson Engineering has completed their 60% Design for the Road Improvements. Woodson Engineering and City Staff met with the residents impacted by the project on March 16, 2016 and will consider a revised design concept that will acknowledge the following concerns of the residences: Preserve all trees to the extent feasible No sidewalk Keep road as narrow as possible Consider Traffic Calming elements in the design Re-Evaluate Hydrology to determine the feasibility of not focusing all drainage to one location. Consider the adequacy of existing drainage swales. The use of curbing would be considered for managing drainage only Consider "rural" nature of neighborhood Match adjacent existing pavement road widths Address drainage outfall volumes and velocities to not impact existing drainage facilities.

Based on the residential meeting, these items will be addressed in the 90% design to the extent feasible. The scope of work was recently increased to include replacement of the water main in the area up to White Spar Road and to loop the system around Warne Street. The 90% design plans are scheduled to be completed in the Fall, 2017, at which time another meeting will be set up with the impacted residences.

City Contact Information Project Manager: Jeff Low 777-1643 Email: Jeff.Low@prescott-az.gov

Last updated: Tuesday, November 28, 2017 at 10:54 AM

PDF Project Update      Traffic Update / Street Closure not available

The design project has been awarded to Entellus, Inc.

The project will remove two aged lift stations (1958) from the collection system by extending approximately 1,500 LF of new 8-inch gravity sewer mains to serve the City parcels located on Mingus, Douglas and Delano Avenues. The existing force mains will be drained and plugged, and the existing wet wells, pumps, and electrical equipment will be removed as part of the project.

The project was identified by the Wastewater Model as a project that will increase operational efficiency of the wastewater collection system. At the completion of this project, the wastewater operations group will have two less lift stations to operate and maintain.

Entellus, Inc. is currently working on survey with 15% alignment plans anticipated later this Fall. See vicinity map below.

Last updated: Tuesday, November 28, 2017 at 10:54 AM

PDF Project Update      Traffic Update / Street Closure not available

The N. Washington Avenue/Churchill Street Reconstruction Project generally consists of constructing roadway improvements on N. Washington Avenue from Churchill Street to Sheldon Street, and on Churchill Street from N. Washington Avenue to Arizona Avenue.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Tuesday, November 28, 2017 at 1:39 PM

PDF Project Update      Traffic Update / Street Closure not available

The project generally consists of repairs to the North Tank East at the terminus of Douglas Avenue off of Willow Creek Road.

The intention is to take the tank offline in October, 2017 to conduct a condition assessment to determine repair needs. Once those needs are identified, plans will be generated for the needed repairs.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Tuesday, November 28, 2017 at 1:40 PM

PDF Project Update      Traffic Update / Street Closure not available

The Penn Avenue/Eastwood Drive Improvements Project generally consists of constructing roadway improvements on Penn Avenue from Gurley Street to Carleton Street; Eastwood Drive from Carleton Street to Nevada Drive; Nevada Drive up to Devereaux Drive; and all cul-de-sacs west of Eastwood. The project will include the following improvements:

-Pavement Reconstruction -Water and Sewer System Replacement -New Storm Drain System in Eastwood Drive -Acker Park Trailhead Improvements -Regional Storm Detention System -Improved Open Space Access

Granite Basin Engineering was selected as the design engineer for this project. The Engineer has completed the 90% design plans. A second public meeting was held on May 10th, to go over the project with impacted residences.

Based off the current City Budget, the design will stop and the project will commence once the City has the budget to construct the project in a few years.

City Contact Information Project Manager: Jeff Low 777-1643

Last updated: Tuesday, November 28, 2017 at 1:58 PM

PDF Project Update      Traffic Update / Street Closure not available

The Robinson Drive Improvements Project consists of the reconstruction of Robinson Drive from Gurley Street to the County boundary south of Newport Drive, including water, sewer, and drainage improvements.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Tuesday, November 28, 2017 at 1:42 PM

PDF Project Update      Traffic Update / Street Closure not available

The S. Washington Avenue/Goodwin Street Improvements Project generally consists of constructing roadway and pedestrian access improvements along E. Goodwin Street from S. Mt. Vernon Avenue to Penn Avenue, and along S. Washington Avenue from Gurley Street to the southerly termination of S. Washington Avenue. Water, sewer and drainage will be updated with the project.

Shephard-Wesnitzer Engineering was selected as the design engineer for this project. Two public meetings are anticipated with the design.

Currently, Shephard-Wesnitzer Engineering has completed the 60% design plans and is finalizing the utility alignments.

The first community open house meeting was held at the Prescott Police Department, 222 Marina Street on April 7th. The second project meeting will be held after the 90% Plan have been completed.

Based off the public meeting additional drainage design improvements were added to the project, which include a sediment catch basin at the south end of the alley north of Goodwin Street between Virginia Street and Washington Avenue, and a storm drain system in the alley and in Goodwin Street from the alley to Virginia Street wash.

Shephard-Wesnitzer Engineering should be finalizing the 90% design by January 2018. After the 90% design is complete a public meeting will be held on the project.

Last updated: Tuesday, November 7, 2017 at 2:40 PM

PDF Project Update      Traffic Update / Street Closure not available

The Summit Avenue/McCormick/Beach Street Improvements Project generally consists of reconstructing the severely deteriorated concrete roadway with new asphalt pavement. The project will change Beach Street to a one way street from McCormick towards Summit. New water and sewer upgrades are also included. The project will also include new storm drain improvements. Curb and sidewalk improvements will be included as needed.

City Contact Information Project Manager: Tim Sherwood 777-1130

Last updated: Tuesday, November 28, 2017 at 10:35 AM

PDF Project Update      Traffic Update / Street Closure not available

The project generally consists of replacing the aged and undersized water main and reconstructing the severely deteriorated pavement on Sundog Ranch Road from Prescott Lakes Parkway to the Yavapai Tribe boundary near Yavpe Connector.

Due to budgetary constraints, the project will be designed and constructed in two phases, the first phase being the water main replacement.

City Contact:
Project Manager George Henderson (928) 777-1130

Last updated: Tuesday, November 28, 2017 at 1:45 PM

PDF Project Update      Traffic Update / Street Closure not available

The Sundog Trunk Main Phase B and Highway 89 Lift Station Project are in design. The design project has been awarded to Lyon Engineering and the Lift Station project to Water Works Engineers.

The project is to direct additional sewer flows from the Sundog Wastewater Treatment Plant to the Airport Water Reclamation Facility. The project includes the construction of a new force main from a proposed lift station at the Veteran's Administration Hospital Grounds north along Highway 89 to the northeast corner of Highway 89 and Prescott Lakes Parkway. The new force main will tie into the Sundog Trunk Main Phase A, which is currently under construction.

The project is currently at the 60% design level. Prior to the construction of the projects, easements will be needed from the Veteran's Administration property and Yavapai-Prescott Indian Tribe.

City Contact Information Project Manager: Jeff Low Phone 777-1643

Last updated: Wednesday, November 1, 2017 at 3:54 PM

PDF Project Update      Traffic Update / Street Closure not available

The Sundog Trunk Main Phase C Project will be presented to City Council to award to Lyon Engineering on November 14th.

The Phase C Trunk Main will replace 40 years old, undersized and failing clay and PVC pipe. The sewer main replacement project will reduce sanitary sewer overflows, reduce operations and maintenance costs, remove portions of the sewer system outside of the floodplain, and will complete the overall Sundog Trunk Main Project towards Centralization.

The engineering design is for approximately 12,000 lineal feet of 12-inch through 30-inch diameter gravity sewer main at the following locations (see vicinity map below):

  1. From the intersection of Miller Valley Road and Brannen Avenue, southward on Miller Valley Road, along Miller Creek to a point just east of Miller Creek low water crossing on Lincoln Avenue.
  2. Starting at the eastern end of Sonora Drive, along the edge of Granite Creek under the La Guardia Bridge (Montezuma Street), through Granite Creek Park, across 6th Street and down Henry Street, parallel to E-Z Street, within the Yavapai Prescott Indian Tribe land (YPIT) and then through Veterans Administration (VA) land generally following the old Peavine railroad alignment to a connection designed in the Phase B Project at the southeastern edge of the VA solar Field.
  3. Branch connections to connect sewer mains that currently outfall into the existing sewer trunk main.

The design also includes approximately 1,600 linear feet of 12-inch water main replacement at the following locations:

The intersection of Miller Valley Road and Lincoln Avenue up to a point 80 feet north of the Miller Creek low water crossing on Lincoln Avenue.

Last updated: Tuesday, November 7, 2017 at 2:12 PM

PDF Project Update      Traffic Update / Street Closure not available

This project will consist of design and replacement of the City of Prescott water booster facility (buildings, boosters, electrical, controls) located in the Town of Chino Valley. The new intermediate pump station, tanks and pipeline will reduce pipeline pressure and provide additional tank storage closer to Prescott. It is anticipated that there will be approximately 8-10MG of storage at the facility. The project will coordinate with upgrades to the Chino Valley pumping facility to adjust for lower operating pressures at the Chino Valley Facility.

Last updated: Tuesday, November 28, 2017 at 10:38 AM

PDF Project Update      Traffic Update / Street Closure not available

This project is at 100% design review and is scheduled to go to bid in December, 2018.

This project is located at the intersection of Cortez Street and Leroux Street. New drain ways and drainage infrastructure will be installed around the south and west sides of the parcel. The parking lot will be resurfaced and striped.

Project Manager Benjamin Burns (928) 777-1130

Last updated: Tuesday, November 28, 2017 at 2:00 PM

PDF Project Update      Traffic Update / Street Closure not available

The Willis and Cortez Intersection and Repair Project will consist of a complete reconstruction of the intersection to include the reconstruction of the crosswalks and replacement of the pavers that have been removed. Improvements also include installation of approximately 340 lf of new water main along a new revised alignment on North Cortez Street, including replacement of two (2) fire hydrants and installation of approximately 400 lf of new water main to replace an existing 10" AC line on West Willis Street. This line will tie into the new 10" water line stub installed as part of the Montezuma Street Project.

City Contact Information Project Manager: Tim Sherwood 777-1130

Last updated: Tuesday, November 28, 2017 at 1:13 PM

PDF Project Update      Traffic Update / Street Closure not available

This project will consist of relocating the existing Zone 7 pump station that feeds pressure zones east of Prescott Lakes Parkway, eastward to the new 1.5 MG water storage tank for pressure Zone 56, and relocated and upgraded to meet existing and future domestic and fire flow demands for this area. This project would include installation of new pumps, associated controls and appurtenances, and an above-ground building enclosure. This project would be concurrent with the installation of the new Zone 56 1.5 MG tank and piping.

City Contact Information Project Manager: Tim Sherwood 777-1130

Last updated: Tuesday, November 28, 2017 at 10:39 AM

PDF Project Update      Traffic Update / Street Closure not available

90% Plans should be received by January, 2018. The project should go to bid during the spring of 2018.

This project will include replacement of the Zone 16 Tank inside the Hidden Valley Ranch, upsizing of the water main in Haisley Road from Senator Highway to Valley Ranch Circle, upsizing of the Virginia Pump Station, and upsizing of the water main from the termination of South Virginia Street to the Prescott Community Church property.

Project Manager Benjamin Burns (928) 777-1130

Last updated: Tuesday, November 28, 2017 at 1:14 PM

PDF Project Update      Traffic Update / Street Closure not available

The Zone 24 & Zone 27 Water Main Piping Replacement Project will consist of various water distribution main improvements within water system Pressure Zone 24 and Zone 27 in the western part of Prescott. The project will include the installation of a new 12-inch water main from the Thumb Butte Drive and Sherwood Road intersection to the new Zone 27 Reservoir on Skyline Drive, and a new 12-inch water main from the Zone 24 Reservoir at Lookout Lane to the new Zone 27 Reservoir.

City Contact Information Project Manager: Tim Sherwood 777-1130

Last updated: Tuesday, November 28, 2017 at 10:45 AM

PDF Project Update      Traffic Update / Street Closure not available

The project generally consists of removing two existing 200,000 gallon water storage tanks and replacing with a single 1.5 million gallon water storage tank. The project includes replacing the existing Mingus Pump Station to meet demands and upsize the pipeline between the pump station and the new tank.

The project is in the conceptual stage. Selection of a design engineer is anticipated in August, 2017.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Tuesday, November 28, 2017 at 2:10 PM

PDF Project Update      Traffic Update / Street Closure not available

The Zone 56 Tank and Piping Project generally consists of constructing a new partially buried 1.5 million gallon pre-stressed concrete tank to be located north of Highway 69 adjacent to York Motors. This tank will replace the existing 100,000 gallon welded steel tank located in Prescott Canyon Estates. An additional project element will include removing and replacing approximately 4,300 lineal feet of existing 8-inch CIP water line with a new 16-inch DIP water line.

City Contact Information Project Manager: Tim Sherwood 777-1130

Last updated: Tuesday, November 28, 2017 at 10:45 AM

PDF Project Update      Traffic Update / Street Closure not available