The City of Prescott (City) and their contractor, Sunland Asphalt & Construction, are currently working on a pavement preservation and maintenance project along Prescott Lakes Parkway, between SR89 and SR69, and along SR89, between Yavpe Connector and the Willow Lake Road roundabout. Due to unforeseen circumstances, we have revised our project schedule which is highlighted below. The project is still scheduled to be completed on time, however, the order of work has changed.
THE REVISED SCHEDULE IS AS FOLLOWS:
Prescott Lakes Parkway, from SR89 to SR69:
To be complete by Friday, August 22: Asphalt milling and preparation work.
Rescheduled to September 3 and September 4: Pavement repairs.
Rescheduled to September 8 through September 18: Two-step pavement preservation application.
Rescheduled to September 24 through September 26: Raising utility covers to the finished road grade and roadway striping.
SR89, from Yavpe Connector to the Willow Lake Road roundabout:
September 2 to September 5: Pavement repairs.
September 15 to October 3: Asphalt milling and paving operations.
Rescheduled to October 6 through October 10: Raising utility covers to the finished road grade and roadway striping.