The project consists of additions and improvements to the Airport Water Reclamation Facility dewatering operations, to include the addition of one (1) new building, two (2) centrifuges or dewatering units, and one (1) 1M-1.5M gallon solids holding tank which will ensure the City has the capacity and redundancy for centralizing wastewater processing at the AWRF facility.
The City advertised an RSOQ in April, will start reviewing the SOQs in May, and plans to award an engineering contract by summer 2024. Bidding and awarding a construction contract will occur in late summer 2025, starting construction in the fall of 2025, and construction is scheduled to be complete in late 2026.