Project Update

The Phase C2 Trunk Main will replace aging, undersized and failing clay and PVC pipe. The sewer main replacement project will reduce sanitary sewer overflows, reduce operations and maintenance costs, and will complete the overall Sundog Trunk Main Project towards Centralization. The project is anticipated to replace approximately 12,000 lineal feet of 12-inch through 30-inch diameter gravity sewer main at the following locations.

1. From the intersection of Miller Valley Road and Brannen Avenue, southward on Miller Valley Road, along Miller Creek to a point just east of Miller Creek low water crossing on Lincoln Avenue.

2. Starting at the eastern end of Sonora Drive, along the edge of Granite Creek under the La Guardia Bridge (Montezuma Street), through Granite Creek Park, across 6th Street and down Henry Street, parallel to E-Z Street, within the Yavapai Prescott Indian Tribe land (YPIT) and then through Veterans Administration (VA) land generally following the old Peavine railroad alignment to a connection designed in the Phase B Project at the southeastern edge of the VA solar Field.

3. Branch connections to connect sewer mains that currently outfall into the existing sewer trunk main.

The project will also include approximately 1,600 linear feet of 12-inch water main replacement at the following locations:

The intersection of Miller Valley Road and Lincoln Avenue up to a point 80 feet north of the Miller Creek low water crossing on Lincoln Avenue.