Skip to Content or Accessibility Information

City Construction Projects

Are you curious about what construction projects are taking place throughout Prescott? Well, you've come to the right place! Below you will find a list of construction projects that are currently underway as well as those projects that are still pending.

For information on the status of construction projects please call the City of Prescott Public Works Department at 928-777-1130.

Projects Currently Under Construction

This project will consist of design and construction of a new 5 million gallon welded steel water tank. The new tank will reflect the nominal dimensions and exact base elevation of the current tank located at the City's Water Production Facility in the Town of Chino Valley and will be located to the east of the existing tank. The proposed tank location will require grading and engineered fill work for the tank pad as well as piping to connect the tank to the existing system. The project will include some minor landscape work, and site security will be incorporated into the new tank project.

The construction project was awarded to Fann Contracting on May 9, 2017. Grading work for the tank pad is nearly complete. Steel delivery and construction of the tank should begin in early August. The contractor will continue with site improvements while the tank construction is underway. There are no impacts to traffic or residents anticipated with this project. Construction should be completed by January 2018.

Last updated: Friday, August 4, 2017 at 10:53 AM

PDF Project Update      Traffic Update / Street Closure not available

The City of Prescott and their contractor, Capital Improvements LLC, are set to begin a road and utility upgrade project the week of October 2nd. The project consists of replacing undersized water and sewer main lines, road improvements, and installing new water service connections for residents. In addition to this work, curb and gutter, sidewalk, and driveway replacements will be performed as needed.

This project is part of an ongoing program to replace deteriorated and undersized main lines within the City utility system. Once complete, these upgrades will increase service reliability and main line capacity for the Dexter Neighborhood and surrounding areas. Project completion is scheduled for spring 2018.

Last updated: Friday, September 29, 2017 at 1:12 PM

Project Update      Traffic Update / Street Closure not available

The Marina Street Pavement and Utilities Upgrade Improvements Project generally consists of reconstructing the existing roadway with new asphalt pavement from Goodwin Street to Gurley Street. New water and sewer upgrades are also included. Curb, sidewalk, and landscape improvements will be included as well.

The construction contract was awarded to Fann Contracting on June 27, 2017. Work is anticipated to begin on August 1, beginning with the sewer main installation starting at Goodwin Street and going north.

City Contact Information Project Manager: George Henderson 777-1130

PDFMarina Street Open House Notice 3-24-16

Last updated: Monday, October 16, 2017 at 10:50 AM

Project Update      Traffic Update / Street Closure not available

The Rosser Street Reconstruction Project Phase IV generally consists of the reconstruction of Rosser Street with new asphalt pavement and replacement of concrete flatwork where found to be defective. Replacement of water and sewer systems is not contemplated at this time.

The project limits are Rosser Street from Campbell Avenue to the easterly boundary of The Meadows at Eagle Ridge Unit III subdivision.

The engineering design contract was awarded to Plateau Engineering in April, 2014. There have been some design delays incurred, in particular the drainage component of the project. Increasing the size of the existing storm water detention basin at Campbell Avenue has been added to the project. The plans have been completed and bid advertising commenced on October 8, 2017. Bid opening is scheduled on November 9, 2017. Construction is programmed to start in early, 2018.

City Contact Information Project Manager: George Henderson, 777-1130

Last updated: Tuesday, November 7, 2017 at 2:58 PM

PDF Project Update      Traffic Update / Street Closure not available

The SR89 Widening and Roundabout Project consists of widening the existing 2 lane roadway to a 4 lane roadway from the current traffic interchange at SR89A south for approximately 4,400 feet, and will include a new roundabout on State Route 89 at a future intersection near the vicinity of the Phippen Museum. The project will also include a new parking area for access to the City's Constellation Trail System.

The construction contract was awarded to Asphalt Paving and Supply on July 25, 2017. Work is anticipated to begin by mid-August. The project is anticipated to take 9 months to complete.

Last updated: Tuesday, November 7, 2017 at 4:03 PM

Project Update      Traffic Update / Street Closure not available

The City of Prescott and their contractor, Fann Contracting, Inc., are currently working on a utility upgrade project at the Sundog Wastewater Treatment Plant. The project includes construction of a wastewater lift station and installation of a new sewer main line. Once complete, the lift station will force wastewater through the main line to a junction structure located north of the Willow Lake Road Roundabout at Lillian Lane and Highway 89 (Northwest corner).

This utility upgrade is the first of several phases to centralize wastewater collection and treatment throughout the municipal system. Once complete, the City's wastewater utility system will direct all effluent to the expanded Airport Water Reclamation Facility. This phase is scheduled for completion in winter 2018.

City Contact Information Project Manager: Jeff Low Phone 777-1643

PDFSundog Sewer Trunk Main Phase A Map

Last updated: Tuesday, November 7, 2017 at 2:18 PM

Project Update      Traffic Update / Street Closure not available

The project generally consists of constructing a new water booster pump station at the southwest corner of Pioneer Parkway and Willow Creek Road. The pump station will provide the ability to utilize Airport area water production facilities (wells) to supplement the Chino Valley Water Production Facility.

Waterworks Engineers is the design engineer. Design plans have been completed. The contract procurement process has been completed. The construction contract was awarded to Schofield Civil Construction on June 27, 2017. Due to long lead times for procurement of specialized equipment, construction will start the end of August, 2017.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Friday, September 15, 2017 at 12:38 PM

Project Update      Traffic Update / Street Closure not available