Skip to Content or Accessibility Information

City Construction Projects

Are you curious about what construction projects are taking place throughout Prescott? Well, you've come to the right place! Below you will find a list of construction projects that are currently underway as well as those projects that are still pending.

For information on the status of construction projects please call the City of Prescott Public Works Department at 928-777-1130.

Projects Currently Under Construction

This project is for street, water quality and streetscape improvements on Alarcon Street from Sheldon Street to E. Gurley Street. Improvements to Alarcon Street include pavement replacement. This project will also include streetscape beautification, and drainage improvements on Alarcon Street. The pavement surface has deteriorated with age and full reconstruction is required.

Last updated: Tuesday, March 21, 2017 at 3:32 PM

Project Update      Traffic Update / Street Closure not available

FY17 Pavement Rehabilitation and Preservation Project

Last updated: Tuesday, August 30, 2016 at 8:20 AM

Project Update      Traffic Update / Street Closure not available

The project generally consists of replacing existing concrete filled, metal pan stair treads and landings with new pre-cast concrete treads and landings at the City owned parking garage at 135 S. Granite Street in downtown Prescott, Arizona. The project also includes renovation of handrails and other associated items as described in the plans and specifications.

DFDG is the engineering design firm. The plans have been completed and bid advertising is underway. Bid opening is scheduled for February 9, 2017. Construction is expected to commence in Spring, 2017.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Thursday, January 26, 2017 at 10:31 AM

PDF Project Update      Traffic Update / Street Closure not available

The project generally consists of installing sport lighting at the Prescott Rodeo Grounds, to include associated electrical improvements.

Darcor, Inc. is the engineering design firm. The plans have been completed. Bid advertising has been completed and a construction contract has been awarded to Banicki Construction. Construction started in January, 2017.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Thursday, March 2, 2017 at 1:46 PM

PDF Project Update      Traffic Update / Street Closure not available

The project generally consists of upgrading existing electrical systems, demolition of various structures and objects, improvements to the vending areas, lead-based paint encapsulation, painting, foam coating on the grandstands roof, utility improvements, cooling systems, and various other improvements as shown on the plans and as defined in the specifications.

Darcor, Inc. is the engineering design firm. The plans have been completed. Bid advertising has been completed and a construction contract has been awarded to Fann Environmental to construct the improvements. Construction commenced in February, 2017.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Thursday, March 2, 2017 at 1:50 PM

PDF Project Update      Traffic Update / Street Closure not available

The Sundog Trunk Main Phase A and Sundog Wastewater Treatment Plant Lift Station Project is about to start construction. The construction projects are scheduled to go to City Council on February 28, 2017 for award of the force main project to Fann Contracting and the Lift Station project to TBD (bid opening on February 9th).

The project is to direct sewer flows from the Sundog Wastewater Treatment Plant to the Airport Water Reclamation Facility. The project includes the construction of a new force main from the new proposed lift station at the Sundog WWTP to the existing gravity main at Lillian Lane and State Route 89. Construction of both projects should start in March and will last 240 calendar days. See attached Sundog Trunk Main Projects map.

City Contact Information Project Manager: Jeff Low Phone 777-1643

PDFSundog Sewer Trunk Main Phase A Map

Last updated: Monday, February 6, 2017 at 10:56 AM

PDF Project Update      Traffic Update / Street Closure not available

The primary objective of the project is to improve the floor in the Transfer Station where solid waste is dumped and pushed into a pit for loading into transfer trailers. The existing floor slab has been worn down and requires remediation. The project also includes the replacement of the scales entering and exiting the Transfer Station.

In November, 2014, proposals were requested from design structural engineers. The firms were ranked and SCS Engineering was the top ranked firm. After an initial study was conducted a contract amendment was executed on June 24, 2015 to proceed with design work. The plans are complete and bid advertising is underway.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Wednesday, January 25, 2017 at 3:59 PM

PDF Project Update      Traffic Update / Street Closure not available

The primary objective is to provide paving and drainage improvements and electrical upgrades at the existing facility. The project is intended to be broken into 4 phases with the first phase being the electrical improvements.

Shephard-Wesnitzer is the engineering design firm. The plans have been completed for the first phase, Transfer Station Electrical Improvements. Bid advertising has been completed and a construction contract has been awarded to AJP Electric. Construction started in February, 2017.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Thursday, March 2, 2017 at 1:51 PM

PDF Project Update      Traffic Update / Street Closure not available

The Tank Maintenance Program generally consists of making repairs to existing water storage tanks to stop leakage and prevent future leakage.

City staff is currently working on developing standards by which repairs will be made. The first water tank programmed for rehabilitation is the South Reservoir at the southerly terminus of S. Washington Avenue.

The plans have been completed and a construction was awarded to Revolution Industrial to complete the repairs to the South Tank. Construction is underway.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Thursday, March 2, 2017 at 1:52 PM

PDF Project Update      Traffic Update / Street Closure not available